The Monday Morning Building Product Advisor
|
The project isnât dead, and it hasnât been handed off to another architect. For now, itâs just sitting on a shelf.
We finished the drawings months ago. Everything was specified, coordinated, and ready to bid. But the project went quiet because itâs waiting for USDA funding approval before it can move forward.
Weâve seen that wait stretch to 6 months on past projects.
Iâve noticed that most product reps think a finished set of documents means the project is moving forward right away. Thatâs not always true. Sometimes, itâs just sitting on a shelf, and the reason isnât about the design.
And itâs usually completely out of the architectâs hands. But it's helpful for you to understand that it does happen.
From what I hear from other architects, HUD approvals can work the same way for multifamily and public housing projects. AndâŚ
Each agency has its own timeline, but the result is the same. The documents are finished, but the project isnât moving forward right away.
Now, there are other situations where a project does actually die on the vine.
Recently, a rep reached out to ask about a project where he had helped me with some waterproofing details. I checked with the lead architect and found out the developer went out of business. Now weâre waiting to see if a new developer picks up the original plans.
In most cases, product reps donât check in to find out why.
âŚAnd most architects wonât send an update to every rep who helped us. Weâve usually moved on to other projects to keep our time billable during the wait.
The waiting period isnât wasted time. Itâs actually an opportunity, but most product reps miss it.
Maybe your product has a few changes or updates. If itâs the architectâs Basis of Design, we would like to know whether we need to make a few quick fixes to the spec.
If there were a code change during the wait, weâd really appreciate a heads-up on how it might affect our project.
If a productâs lead times change and you have a simple fix for the specs, the waiting period is the perfect time to tell your architect. We arenât under bid pressure, so we may have time to review and update things before the documents are finalized.
What you donât want to do during this lull is pitch something new that wasnât already part of the project.
Save that conversation for another time for the next project.
Once funding is approved and the project goes out to bid, simple changes can become more complicated.
A product update that could have been handled with a quick email during the waiting period now needs an addendum or a change order. That takes longer, creates more paperwork for us, and honestly, weâre much less likely to make the change once weâre busy with other bidding tasks.
So donât wait for the RFP or a call from the contractor. If you know a project is delayed by USDA, a school bond, or something else, ask your architect directly if itâs on hold.
Then make the most of that time.
The rep who called me last week will send me a product update before the project goes out to bid. And I can make a quick change to 2 or 3 lines in the spec. And itâs not because heâs lucky⌠Itâs because he simply asked.
If you have a project that might be on hold right now, reply and let me know what funding source itâs waiting on. Iâll let you know if thatâs a normal delay or something you should ask about.
â
That's it for this week!
Here's to building more than just buildings, and see you next week,
Neil Sutton
âArchitect | Speaker | The Product Rep Coach
=======
P.S. Do you really want inside an architect's head?
When youâre ready, there are 3 ways you can start working with me:
=======
âIf this was forwarded to you, go to â mmbpa-newsletter(dot)carrd(dot)co â so you donât miss the next lesson.
â=======
Connecting with architects should be simple. I'm a veteran architect (28+ years) who's been helping architectural product reps get even better at it for 11 years. So we're all working toward a stronger industry. Get the weekly insights by signing up here.
The Monday Morning Building Product AdvisorIssue #140 Last month, I was at a red light and looked up at a building I worked on some 8 or 9 years ago. The panels are chalking. They arenât failing, just showing that dusty, faded look you see when a finish starts to wear out. Itâs uneven, so the south side looks much older than the west. And I remember the exact meeting that caused it. It was a value engineering meeting about 5 weeks before bidding. As usual, we were over budget. There were 11...
The Monday Morning Building Product AdvisorIssue #139 Back in 1974, two researchers showed 45 students a film of a car crash and then asked them one question: âAbout how fast were the cars going when they hit each other?â Except they didnât use the word âhitâ with everyone. Some heard âsmashed into.â Others heard âbumped,â âcollided with,â or âcontacted.â It was the same footage and the same crash, but only one word was different. Not the actual footage from the 1974 study The people who were...
The Monday Morning Building Product AdvisorIssue #137 Steadfast Steve, Part 2 We found ourselves 900 miles away in Wausau, Wisconsin, sitting at a table to review the shop drawings before they were officially submitted. If you missed last week, hereâs a quick recap⌠Steadfast Steve spent around 3 years helping our teams solve curtain wall details, often on projects he wasnât likely to win. When the research campus moved to phase two, he put in a substitution request for the new system he...